13.01.2020 – Implementation of the project is completed

In order to reduce operating costs caused by a high degree of wear of the equipment in use, it was decided to modernize the air separation unit in terms of replacement of the cryogenic process pumps of the НКПМ2-50/63 type with high-performance cryogenic centrifugal process pumps MCP 190/20L-3.3-CB-WB C/0 manufactured by CRYOSTAR SAS, France.

The project provided:

  1. Development of design documentation.
  2. Dismantling of existing pumps НКПМ2-50/63.
  3. Installation of pumps MCP 190/20L-3.3-CB-WB C/0, valves and pipelines.
  4. Production and installation of an automatic control system for cryogenic pumps.
  5. Commissioning and start-up.

The construction object is located on the territory of the oxygen station in the air separation workshop of PJSC AMKR.


News

11.02.2019 – Отгружена станция наполнения углекислотных огнетушителей СНУ-2-25/7,3

Отгружена станция наполнения углекислотных огнетушителей СНУ-2-25/7,3

13.01.2020 – Implementation of the project is completed

A turnkey project of the air separation unit modernization in terms of replacement of cryogenic process centrifugal pumps at PJSC ArcelorMittal Kryvyi Rih

19.11 – 22.11.2019 – XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019 was held

CRYO INTER TRADING took part in the XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019

05.11.2019 – XIII INTERNATIONAL INDUSTRIAL FORUM – 2019

LLC CRYO INTER TRADING will take part in the XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019. Specialized industrial exhibition in the field of metalworking, mechanical engineering and related industries

24.10.2019 – Replenishment of the warehouse with cryocylinders

The warehouse is replenished with three types of cryo-cylinders with a hydraulic volume: 195 l, 210 l and 480 l

2019 Cryo Inter Trading
All rights reserved