18.10.2019 – Liquid nitrogen storage and distribution system project was implemented

A turnkey project of the liquid nitrogen storage and distribution system construction was implemented at the LLC Service Oil, Poltava. Construction works were performed in three stages:

1. Development of design documentation.

2. Equipment supply:

  • shipment of modular cryogenic pumping station of our own production on the basis of the cryogenic centrifugal pump GBS 155/4.5-5.5 C/3 made by CRYOSTAR S.A.S., France for liquid nitrogen pumping;
  • shipment of a cryogenic tank of 80 m3 for storage of liquid nitrogen.

3. Installation and commissioning.


News

11.02.2019 – Отгружена станция наполнения углекислотных огнетушителей СНУ-2-25/7,3

Отгружена станция наполнения углекислотных огнетушителей СНУ-2-25/7,3

13.01.2020 – Implementation of the project is completed

A turnkey project of the air separation unit modernization in terms of replacement of cryogenic process centrifugal pumps at PJSC ArcelorMittal Kryvyi Rih

19.11 – 22.11.2019 – XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019 was held

CRYO INTER TRADING took part in the XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019

05.11.2019 – XIII INTERNATIONAL INDUSTRIAL FORUM – 2019

LLC CRYO INTER TRADING will take part in the XVIII INTERNATIONAL INDUSTRIAL FORUM – 2019. Specialized industrial exhibition in the field of metalworking, mechanical engineering and related industries

24.10.2019 – Replenishment of the warehouse with cryocylinders

The warehouse is replenished with three types of cryo-cylinders with a hydraulic volume: 195 l, 210 l and 480 l